What Is a Deadman Anchor and How Do I Install One in a Retaining Wall?

A deadman anchor is a horizontal tie buried behind a retaining wall to stop it tipping forward. Learn how they work and how to install them correctly.

What Is a Deadman Anchor and How Do I Install One in a Retaining Wall?

A deadman anchor is a horizontal timber or other structural member buried into the retained soil behind a retaining wall and connected to the wall face, preventing the wall from rotating or sliding forward under soil pressure. They are one of the most common and effective stabilising methods for timber sleeper retaining walls, and installing them correctly is essential for a safe, long-lasting structure.

Why Retaining Walls Need Deadman Anchors

Soil exerts significant lateral (sideways) pressure against any retaining wall — a force that increases with wall height, soil type, and moisture content. Without adequate anchorage, even a well-built wall can slowly lean forward and eventually fail. Deadman anchors work by transferring that lateral load back into the stable soil mass behind the wall, effectively using the weight of the earth itself as a counterbalance.

For timber sleeper walls taller than about 600–800 mm, deadman anchors are generally considered best practice. For walls over 1.5 m in height, they are typically essential — and building consent is almost certainly required (more on that below).

Do You Need a Building Consent?

In New Zealand, retaining walls are regulated under the NZ Building Code. As a general guide:

  • Retaining walls up to 1.5 m in height may be exempt from consent under Schedule 1 of the Building Act, provided they meet certain conditions (no surcharge loading, not near boundaries or structures, stable ground).
  • Walls over 1.5 m, or any wall with additional loads (driveways, buildings, slopes above), will almost certainly require a building consent.

Always confirm with your local council before starting work — exemptions have conditions that vary by site. Check MBIE Building Performance for guidance on Schedule 1 exemptions.

What You'll Need

  • H5-treated timber for deadman members and wall sleepers (ground contact, high-decay-risk environment)
  • Galvanised or stainless steel coach screws or bolts (minimum 12 mm diameter)
  • Geotextile fabric (optional but recommended to prevent soil migration)
  • Compactable backfill (gravel or AP20 aggregate)
  • Spade, level, tape measure, drill, and appropriate bits
  • Safety glasses and gloves

Safety note: Retaining wall construction involves heavy materials and excavation. Be aware of underground services before digging — call Dial Before You Dig (0800 248 344) first. If working near slopes or unstable ground, assess the risk of collapse carefully.

How a Deadman Anchor Works

A typical deadman assembly consists of:

  1. A tie-back member — a horizontal timber running at 90° back into the hillside from the wall face.
  2. A deadman log or plate — a shorter timber fixed perpendicular to the tie-back at its buried end, forming a T or L shape that grips the soil.
  3. A connection to the wall face — usually bolted through the face sleeper.
ComponentTypical Size (H5 Timber)Spacing
Tie-back member200×75 mm or 200×50 mmEvery 1.2–1.8 m along wall
Deadman plate600–900 mm long, same sectionOne per tie-back
Coach bolts12–16 mm galvanised2 per connection point

Sizes and spacing should be confirmed by a structural engineer for walls over 1.5 m or in challenging ground conditions.

Step-by-Step Installation

1. Plan Your Layout

Mark deadman positions along the wall every 1.2–1.8 m. They are typically installed at one-third to one-half the wall height up from the base — so for a 1.2 m wall, roughly 400–600 mm up from the footing course.

2. Excavate the Tie-Back Trench

Dig a trench running horizontally back into the slope at each deadman location. The trench should extend at least 1.5× the wall height back into the retained soil — for a 1.2 m wall, that's at least 1.8 m back. The trench depth should match the timber height plus a little clearance.

3. Assemble the Deadman

Cut your tie-back timber to length. Fix the deadman plate perpendicular across the far end using galvanised coach screws, forming a T-shape. Pre-drill to avoid splitting.

4. Connect to the Wall Face

Before placing the course of sleepers that will sit at deadman height, position the inner end of the tie-back so it overlaps the back of the wall sleeper by at least 300 mm. Bolt through with two galvanised coach bolts.

5. Backfill and Compact

Lay geotextile fabric over the deadman assembly if desired, then backfill the trench with compactable gravel in 150 mm layers, compacting each layer firmly. Avoid using expansive clay soils as backfill — they retain water and increase pressure on the wall.

6. Continue Building the Wall

Continue laying sleeper courses above the deadman level, staggering vertical joints for strength. Ensure adequate drainage (agricultural drain pipe or gravel drainage layer) behind the wall to prevent hydrostatic pressure build-up.

When to Call a Professional

While a straightforward single-tier sleeper wall with deadman anchors can be a rewarding DIY project, there are situations where you should engage a qualified retaining wall builder or structural engineer:

  • The wall exceeds 1.5 m in height
  • There are structures, driveways, or slopes above the wall
  • The ground is soft, wet, or unstable
  • You need a building consent (an LBP may need to sign off restricted building work — check Licensed Building Practitioners)
  • The wall is near a property boundary

You can find experienced local retaining wall builders on tradedirectory.co.nz.

Frequently Asked Questions

How far back into the soil should a deadman anchor extend?+

As a general rule, the tie-back should extend at least 1.5 times the wall height back into the retained soil. For example, a 1.2 m wall would need deadman tie-backs reaching at least 1.8 m behind the wall face. For taller or more complex walls, a structural engineer should specify the exact length.

What timber should I use for deadman anchors in NZ?+

Always use H5-treated timber for any timber in direct ground contact in a retaining wall application. H5 treatment is rated for ground contact in high-decay-risk situations. Check with your local timber supplier (such as PlaceMakers or Mitre 10) to confirm you're getting the correct treatment level.

Do I need a building consent to install a retaining wall with deadman anchors?+

It depends on the wall height and site conditions. Walls up to 1.5 m may be exempt from consent under Schedule 1 of the Building Act, but this depends on factors like surcharge loading, proximity to boundaries, and ground conditions. Always check with your local council before starting, and visit MBIE Building Performance (building.govt.nz) for guidance.

How often should deadman anchors be spaced along a retaining wall?+

Typically every 1.2 to 1.8 metres along the wall length, but this depends on wall height, soil type, and loading conditions. For walls requiring building consent, spacing should be confirmed by a structural engineer as part of the consented design.

Can deadman anchors be used with concrete block or concrete sleeper retaining walls?+

Deadman anchors are most commonly associated with timber sleeper walls, but the principle is used in other wall types too — for example, geogrid reinforcement in segmental block walls works on a similar concept. For concrete or masonry walls, the connection method and materials will differ significantly, and engineering input is strongly recommended.

Need a Retaining Wall Builder?

Find qualified retaining wall builders near you in our directory.

Find a Retaining Wall Builder →

Retaining Wall Builders Near You

Oncore Property Maintenance and Repairs logo

Retaining Wall Builder

Parnell, Auckland

Oncore Service New Zealand is the country's trusted specialist for residential and commercial maintenance, repairs, insurance work, and installations. From your initial consultation through project completion, we provide a single point of contact—no juggling multiple trades or stress . Whether it’s flood recovery, fire damage, heating upgrades, or Healthy Homes compliance, our local teams handle every detail on time and within budget.

Property maintenance services
Kennedy Contracting logo

Retaining Wall Builder

Christchurch, Canterbury

Christchurch Fencing Contractors and Decking - Kennedy Contracting Licensed Building Practitioner Christchurch’s Trusted Outdoor Construction & Property Improvement Experts Quality construction services for residential and commercial projects across Christchurch and Canterbury. From budget-friendly developments to high-end custom builds. Get Free Quote View Our Work Experienced Outdoor Construction & Landscaping Contractor Serving Christchurch Kennedy Contracting delivers quality...

  • Licensed Building Practitioner (LBP)
Build2 logo

Retaining Wall Builder

Auckland, Auckland

Based in Auckland North Shore Build2 Construction are experts at residential construction and concrete foundations. Contact Auckland's premier builders today

Buildingworks logo

Retaining Wall Builder

Whangarei, Northland

Whangarei region. Buildingworks provides a friendly, reliable, honest service for your residential and commercial building projects.

  • Licensed Building Practitioner (LBP)
Drainways logo

Retaining Wall Builder

Hastings, Hawke's Bay

Looking for reliable drain cleaning services in Hawke's Bay? Drainways offers professional civil drainage solutions. Contact us for a free quote today.

Concrete & Earth Queenstown logo

Retaining Wall Builder

Queenstown, Otago

Concrete & Masonry Stores Near You

Stock up for this job — concrete & masonry suppliers and stores, with address, phone and email.

THE Block Shop NZ Ltd logo

THE Block Shop NZ Ltd

Drury, Drury, Auckland

Concrete & Masonry

The Block Shop (TBS) is an independently owned manufacturer of masonry products in New Zealand. Our range includes kerbstone blocks and grass pavers, known for their insulating benefits, strength, and light weight due to premium local pumice. We supply distributors, builders, and block layers directly. Contact us for quality masonry solutions.

Concrete Pumping Equipment NZ Ltd logo

Concrete Pumping Equipment NZ Ltd

Wellington, Wellington

Concrete & Masonry

Supplying high-quality concrete pumping equipment, spare parts, and technical support across New Zealand. Trusted by contractors nationwide.

Concretec New Zealand Ltd logo

Concretec New Zealand Ltd

Rd 2, Pokeno, Waikato

Concrete & Masonry
Concrete Cowboy Ltd logo

Concrete Cowboy Ltd

Mount Roskill, Auckland, Auckland

Concrete & Masonry
Cemix Products Ltd logo

Cemix Products Ltd

Onehunga, Auckland, Auckland

Concrete & Masonry

We are a leading, independently owned manufacturer of drymix concrete and cement products for the building industry and DIY market in New Zealand

East Coast Concrete Ltd logo

East Coast Concrete Ltd

Awapuni, Gisborne, Gisborne

Concrete & Masonry

East Coast Concrete: Your Concrete Solutions Provider in Gisborne, New Zealand. Providing reliable and innovative concrete solutions for your projects.

Browse all concrete & masonry suppliers →
Last updated: Last reviewed:

The information on this page is provided as a general guide only. Kiwi Trade Directory makes no representations or warranties regarding the accuracy, completeness, or suitability of this information for your specific situation. Costs, timeframes, and recommendations vary significantly depending on your location, property, and individual circumstances. Always obtain multiple quotes from qualified tradespeople and seek independent professional advice before undertaking any home improvement or building work. Kiwi Trade Directory accepts no liability for any loss or damage arising from reliance on the information provided on this site.