When building work is completed in New Zealand, there are specific council documents you should expect to receive — and some that are legally required. Understanding what these documents are, why they matter, and how to follow up if something is missing can save you significant headaches down the track, especially when it comes time to sell your home or make an insurance claim.
The Building Consent
Before work even begins, a building consent should have been issued by your local council (territorial authority). This is the document that gives legal permission for the work to proceed. If your project required a building consent, you should have a copy of this on file. It will include approved plans and specifications that the builder must follow throughout the project.
Not all work requires a building consent — some minor work falls under Schedule 1 exemptions under the Building Act 2004. However, what counts as exempt can be nuanced, so always confirm with your local council before assuming work is exempt. You can find general guidance at MBIE Building Performance.
Inspection Records
During construction, council inspectors visit the site at key stages — for example, foundations, framing, and weathertightness. Each inspection should be recorded. Ask your builder or council for a copy of the inspection records to confirm all required inspections were carried out and passed. If inspections were missed, this can create problems when applying for your final certificate.
The Code Compliance Certificate (CCC)
The most important document you should receive at the end of a consented building project is the Code Compliance Certificate (CCC). This is issued by your local council after a final inspection confirms the completed work meets the requirements of the NZ Building Code.
Key things to know about the CCC:
- It is a legal requirement under the Building Act 2004 for consented work.
- Your builder or project manager typically applies for it on your behalf, but as the homeowner, it is ultimately your responsibility to ensure it is obtained.
- Without a CCC, your property may be harder to sell, refinance, or insure.
- Councils have up to 20 working days to decide on a CCC application once all required information is received.
If your council is not satisfied the work complies, they may issue a Certificate of Acceptance (COA) in some circumstances, or decline to issue a CCC. A COA is a different document and offers more limited assurances — check with your council or a Licensed Building Practitioner (LBP) if you are unsure which applies to your situation.
Record of Title and LIM Updates
Once a CCC is issued, the council updates their records. This information eventually flows through to your Land Information Memorandum (LIM), which is a report councils provide about a property. When you sell your home, buyers will typically request a LIM, and any consented work should appear on it with a corresponding CCC. It is worth ordering a LIM yourself after major work to confirm everything has been recorded correctly.
Producer Statements
For certain types of work — particularly engineering, cladding systems, or specialist installations — your builder or subcontractors may provide producer statements. These are written assurances from a qualified professional (such as a structural engineer) that the work has been designed or constructed to comply with the Building Code. Producer statements are often submitted to council as part of the CCC application and you should receive copies for your records.
Licensed Building Practitioner (LBP) Records
If your project involved restricted building work (RBW) — such as structural work or weathertightness — it must be carried out or supervised by a Licensed Building Practitioner. LBPs are required to provide a Record of Work on completion, confirming what restricted work they carried out. You should receive this document, and a copy also goes to the council. Keep it with your other building documents.
What to Do If Documents Are Missing
- Contact your builder first — they may have the documents or can assist with obtaining them.
- Contact your local council — they hold records of all consented work and can confirm what has been issued.
- If work was done without consent and should have had one, seek advice from your council or an LBP about how to regularise the situation. MBIE Building Performance has guidance on this.
- BRANZ is a useful independent resource for understanding building compliance in New Zealand.
A Summary of Key Documents
| Document | Who Issues It | When You Get It |
|---|---|---|
| Building Consent | Local council | Before work starts |
| Inspection Records | Local council | During construction |
| Code Compliance Certificate (CCC) | Local council | After final inspection |
| Producer Statements | Engineer/specialist | During or after construction |
| LBP Record of Work | Licensed Building Practitioner | On completion of RBW |
When to Call a Professional
If you are unsure whether the work on your home was consented, or if you have purchased a property and cannot locate a CCC for previous building work, it is worth speaking with a qualified builder or LBP. They can help you assess the situation and advise on next steps. You can find trusted local builders on tradedirectory.co.nz.
For electrical or plumbing work carried out as part of your build, note that these trades involve restricted work regulated by the Electrical Workers Registration Board (EWRB) and the Plumbers, Gasfitters and Drainlayers Board (PGDB) respectively. Certificates of compliance for this work should also be in your records.