Installing deck post base brackets on a concrete slab is a straightforward job if you follow the right steps and use the correct fixings. Done properly, it creates a strong, durable connection between your deck posts and the slab while keeping timber up off the concrete to reduce moisture-related decay. Here's how to do it safely and in line with good NZ trade practice.
Do You Need a Building Consent?
Before you pick up a drill, check whether your deck project requires a building consent. In New Zealand, decks under 1.5 m above ground level may qualify as exempt work under Schedule 1 of the Building Act 2004 — however, the exact height threshold and conditions are specific and have changed over time, so confirm the current exemption criteria with your local council, but there are conditions — including that the work must still comply with the NZ Building Code. Always confirm with your local council before starting, as exemptions vary. If your deck is attached to the house, consent is more likely to be required. Work carried out by or supervised by a Licensed Building Practitioner (LBP) gives you added assurance that the job meets code.
Tools and Materials You'll Need
- Post base brackets (e.g., adjustable or fixed-base type, rated for your post size)
- Rotary hammer drill with a SDS masonry bit (sized to your anchor bolt diameter)
- Wedge anchors or chemical anchors (check the bracket manufacturer's specification)
- Torque wrench or impact driver
- String lines and builder's square
- Spirit level
- Tape measure and pencil
- Safety glasses and hearing protection
Safety note: Rotary hammer drills are powerful tools. Always wear eye and hearing protection, and read the tool's safety instructions. If you're hiring equipment, ask the hire shop for a briefing. See WorkSafe NZ for general tool safety guidance.
Step 1 — Lay Out Your Post Positions
Accurate layout is critical. Use string lines and a builder's square (or the 3-4-5 triangle method) to establish square, straight lines across the slab. Mark each post centre point with a pencil or chalk. Double-check your spacings against your deck plans — post positions must match your bearer and joist layout.
Tip: If your deck design follows NZS 3604:2011 (Timber-framed buildings), refer to the span tables for your post, bearer, and joist sizes to confirm post spacing is correct before you drill anything.
Step 2 — Choose the Right Bracket and Fixing
Not all post base brackets are equal. Choose a bracket that:
- Is the correct size for your post (90 mm, 140 mm, etc.)
- Is hot-dip galvanised or stainless steel — especially important in coastal NZ environments where salt air accelerates corrosion
- Is rated for the load it will carry (check the manufacturer's load tables)
For the concrete anchors, you'll typically use either wedge anchors (mechanical expansion bolts) or chemical anchors (epoxy or polyester resin with a threaded rod). Chemical anchors are generally preferred where the concrete edge distance is limited or where higher loads apply. Always follow the anchor manufacturer's minimum embedment depth and edge distance requirements — these are non-negotiable for structural integrity.
You can find a range of suitable products at Bunnings, Mitre 10, or PlaceMakers.
Step 3 — Drill the Anchor Holes
- Using your rotary hammer drill and the correct diameter SDS masonry bit, drill straight down at each marked centre point.
- Drill to the required embedment depth plus a little extra to allow for dust at the bottom of the hole.
- Blow or vacuum out all dust and debris from the hole — this is especially important with chemical anchors, as dust prevents the resin from bonding properly.
Step 4 — Install the Anchors
Wedge Anchors
- Drop the anchor into the hole and tap down with a hammer until the nut and washer sit just above the slab surface.
- Place the bracket over the anchor stud, add the washer and nut, then torque to the manufacturer's specified value.
Chemical Anchors
- Inject resin into the hole following the manufacturer's instructions (usually filling from the bottom up).
- Insert the threaded rod, twisting slightly to distribute the resin evenly.
- Allow the full cure time before applying any load — this varies by product and temperature, so check the datasheet. Sika and Hilti are well-known suppliers of chemical anchor systems in NZ.
Step 5 — Set and Level the Brackets
Once anchors are set and cured:
- Thread the bracket onto the anchor stud (or bolt it down if using a base plate style).
- Use a spirit level to confirm the bracket is plumb and correctly oriented.
- Tighten all fixings to the specified torque.
- If using adjustable post bases, you can fine-tune the height slightly to account for any unevenness in the slab — a useful feature on older slabs.
Step 6 — Install the Posts
Sit the timber post into the bracket cup, check it's plumb in both directions with a spirit level, then fix through the bracket's pre-punched holes using the specified joist hanger nails or bolts (never substitute with standard wire nails). The bracket should hold the post base at least 25–50 mm above the slab surface to allow drainage and airflow, reducing the risk of timber decay.
When to Call a Professional
If your deck is elevated, attached to the house, or in a high-wind or coastal zone, the structural requirements become more complex. A qualified deck builder or LBP can ensure your post sizing, bracket selection, and fixing schedule all meet the NZ Building Code. If consent is required, restricted building work must be carried out or supervised by an LBP. You can find experienced local deck builders on tradedirectory.co.nz.





Licensed Building Practitioner (LBP)