Hand-digging a cable trench in your yard is a job many NZ homeowners tackle themselves — but striking a buried power cable, gas line, or water pipe can be dangerous, expensive, and even fatal. The golden rule is simple: always locate buried services before you put a spade in the ground. Here's how to do it safely and legally.
Understand What Could Be Buried
Under most NZ properties you'll find a mix of services, including:
- Electrical cables (mains supply, submains, outdoor lighting circuits)
- Gas pipes (natural gas or LPG)
- Water supply pipes (council mains and private connections)
- Wastewater and stormwater drains
- Telecommunications cables (copper phone lines, fibre)
Depths vary widely. In NZ, electrical cables are often buried as shallow as 450 mm in private property and gas pipes can be even shallower in some older installations. Never assume a service is deep enough to be safe.
Step 1 — Contact Before You Dig (Mandatory)
Before any excavation, you must contact Before U Dig (BUD) — New Zealand's free utility notification service. Submit a request at beforeudig.co.nz (note: this is a real, well-established NZ service). Network operators will respond with plans showing the approximate location of their assets in your area.
Also check with your local council for any council-owned stormwater, wastewater, or water mains that may cross your property. Plans are not always 100% accurate, so treat them as a guide, not a guarantee.
Step 2 — Mark Up the Site
Once you have the service plans, use marking paint or flags to mark the approximate routes of all buried services on the ground surface. Use the standard NZ/Australian colour coding:
| Colour | Service |
|---|---|
| Red | Electrical power |
| Yellow | Gas |
| Blue | Water |
| Orange | Telecommunications |
| Green | Sewer/drainage |
| White | Proposed excavation area |
Keep your planned trench route as far as possible from marked services.
Step 3 — Consider a Cable/Pipe Locator
Plans show approximate locations — the actual pipe or cable can be offset by 300 mm or more. Hiring a cable and pipe locator (also called a CAT scanner or service locator) from a hire shop such as Bunnings or Mitre 10 gives you a much more precise indication of where live electrical cables run. For gas and water pipes, a locator with both electromagnetic and signal-generator modes works best.
If you're unsure how to use the equipment, or if services are densely packed, consider hiring a professional service locator — they can be found on tradedirectory.co.nz.
Step 4 — Hand-Dig Safely
Once services are marked, follow these safe-dig practices:
- Hand-dig only within 500 mm either side of any marked service. Never use a mechanical excavator, bar, or mattock in this zone.
- Use a flat spade rather than a pointed one to reduce the risk of piercing a cable or pipe.
- Dig slowly and check frequently. If you see unusual colours (yellow gas pipe, red electrical duct, blue water pipe), stop immediately.
- Keep a clear escape route and never work alone near gas or electrical services.
- If you smell gas at any point, stop work, leave the area, and call your gas network operator or 111 immediately. Do not use any electrical switches.
- Wear safety boots, gloves, and safety glasses throughout.
WorkSafe NZ has guidance on excavation safety that applies even to small hand-dug trenches.
Step 5 — Trench Depth and Backfill
For a typical low-voltage cable installation on private property, the NZ Electrical Code of Practice and network operator standards generally require a minimum cover of 450 mm for cables in conduit, though your local lines company may specify more. Always check with your lines company and refer to MBIE Building Performance for relevant Building Code requirements.
When backfilling:
- Lay warning tape (colour-coded to the service) about 150 mm above the cable or pipe.
- Use fine, stone-free material for the first 100 mm of cover directly over the cable.
- Compact backfill in layers to avoid settlement.
Does This Work Need a Building Consent?
Laying a cable trench on your own property for a garden lighting circuit or similar low-risk work may fall under Schedule 1 exemptions of the Building Act — but this depends on the nature of the work and your council's interpretation. Always confirm with your local council before starting. See MBIE Building Performance for guidance on consent exemptions.
When to Call a Professional
Some parts of this work are legally restricted in New Zealand:
- All electrical connection work — connecting cables to your switchboard, making terminations, or any work on the mains supply — must be carried out by a registered electrician licensed under the Electrical Workers Registration Board (EWRB). Homeowners may do some of their own electrical work in certain circumstances, but connecting to the mains is always restricted work. Check with the EWRB for the current scope of what homeowners are permitted to do.
- Gas pipe installation and connection is restricted work under the Plumbers, Gasfitters and Drainlayers Board (PGDB). Never attempt to connect or modify gas lines yourself.
- Plumbing connections to the water supply or wastewater system are also restricted work under the PGDB.
- If your trench is near the boundary, involves shared services, or is deeper than 1.5 m, engage a qualified excavator or civil contractor.
For complex or uncertain situations, a qualified tradesperson will have the right tools, insurance, and legal authority to do the work safely. Find local excavation and trades professionals on tradedirectory.co.nz.






Licensed Building Practitioner (LBP)