Relocating a gutter outlet and running a new downpipe is a project many handy homeowners can tackle themselves — but before you reach for the tin snips, it pays to understand the NZ Building Code requirements, drainage rules, and when a building consent might be needed. Get these details right and you'll end up with a watertight, compliant result that protects your home for years to come.
Understanding the NZ Building Code Requirements
Gutters and downpipes are part of your home's roof drainage system, governed by Clause E1 (Surface Water) and Clause E2 (External Moisture) of the NZ Building Code. The key requirement is that roof water must be collected and discharged in a way that doesn't cause damage to the building or neighbouring properties.
For most residential homes, gutter and downpipe work falls under Schedule 1 of the Building Act 2004, which lists work that is exempt from requiring a building consent. Routine maintenance, repair, and like-for-like replacement of gutters and downpipes is generally exempt. However, adding a new outlet or significantly altering the drainage path may not be exempt — always confirm with your local council before starting work. You can find guidance on what requires consent at MBIE Building Performance.
Where Does the Water Go? Stormwater Connections Matter
This is the part many DIYers overlook. In most NZ urban areas, downpipes must connect to the stormwater drainage system — not to the ground surface, a garden bed, or the sewer. Connecting a new downpipe to an underground stormwater drain is drainlaying work, which is restricted work under the Plumbers, Gasfitters, and Drainlayers Act 2006. It must be carried out by (or under the supervision of) a licensed drainlayer registered with the Plumbers Gasfitters & Drainlayers Board.
If your new downpipe will simply discharge above ground via a splash block or soak pit (where permitted by your council), you may be able to complete the full job yourself. Check with your council first, as rules vary by region and some areas have restrictions on soakage due to soil type or proximity to boundaries.
Tools and Materials You'll Need
- Gutter outlet (round or square, to match your existing gutter profile)
- Downpipe lengths and elbows/offsets (PVC or pressed metal — match your existing system)
- Gutter sealant (such as a product from Sika suitable for gutters)
- Hole saw or jigsaw (for cutting the gutter)
- Tin snips (for metal gutters)
- Pipe clips/brackets and screws
- Tape measure, pencil, spirit level
- Safety equipment — sturdy ladder, non-slip footwear, and ideally a ladder standoff
Step-by-Step: Fitting the Gutter Outlet
1. Plan the outlet position
Choose a location that allows the downpipe to run vertically (or with minimal offsets) to its discharge point. The outlet should be at or near the low point of the gutter run — gutters should fall at least 1:500 (2 mm per metre) toward the outlet. Mark the centre of your new outlet on the gutter.
2. Cut the hole
Using a hole saw or jigsaw (for PVC) or tin snips (for metal), cut the outlet hole to match the outlet fitting size. Deburr any sharp edges carefully.
3. Fit and seal the outlet
Insert the outlet fitting from below and secure it according to the manufacturer's instructions. Apply a bead of gutter sealant around the joint on the inside of the gutter. Allow to cure fully before testing.
4. Run the downpipe
Using elbows and offsets as needed, run the downpipe from the outlet down the wall to the discharge point. Keep the pipe as vertical as possible — excessive bends can cause blockages. Fix the pipe to the wall using pipe clips at intervals recommended by the manufacturer (typically every 1.2–1.8 m).
5. Seal or cap the old outlet
If you're decommissioning an old outlet, fit a gutter stop end or outlet blanking plug and seal thoroughly to prevent leaks.
6. Test the system
Run water from a hose into the gutter and check for leaks at the new outlet joint, correct flow toward the outlet, and proper discharge at the bottom.
NZ Climate Considerations
NZ's variable climate — from heavy West Coast rainfall to Auckland's subtropical downpours — means gutter capacity matters. If you're adding an outlet because your existing system can't cope, check that your gutter size and downpipe diameter are adequate for your roof catchment area. BRANZ publishes guidance on roof drainage sizing that can help you confirm your system is up to the job.
Safety First
Working at height is one of the leading causes of serious injury in NZ. Always use a stable, correctly positioned ladder and never overreach. For single-storey work, a good-quality ladder with a standoff is usually sufficient. For anything above one storey, seriously consider hiring a professional. WorkSafe NZ has clear guidance on safe ladder use for homeowners.
When to Call a Professional
Call a qualified roofer or plumber if:
- Your new downpipe needs to connect to an underground stormwater drain (restricted drainlaying work)
- You're working above single-storey height
- Your roof has complex geometry or the gutter is difficult to access safely
- You're unsure whether a building consent is required
- The existing gutter is damaged, sagging, or incorrectly graded
A licensed professional will ensure the work is compliant and can handle any consent paperwork. You can find experienced local roofers and plumbers on tradedirectory.co.nz.





Roofing Association of NZ (RANZ)
Licensed Building Practitioner (LBP)